Jenney Pond and Town Brook Construction in Plymouth: Spring 2027

October 22, 2026

Spring Lane looks different now. The power line that used to hang over the road above the Jenney Pond dam is gone, buried along with a new gas line and a new water main. Concrete sidewalks are poured and waiting for their brick finish. Behind the Plimoth Grist Mill, the old garden has been torn out, and retaining walls for a new accessible walkway step down toward the lower mill area.

The project is now in its second full year of construction, and anyone who walks between Jenney Pond and Brewster Gardens has had time to wonder why it is taking so long. The engineering is substantial, but much of the calendar on the $20.9 million Town Brook project is set by the river herring, and that explains the seasons when work happens, why the walkways slipped, and what the corridor will be measured against once it opens.

Two Windows the Fish Control

Town Brook carries one of the oldest herring runs in the region. Each spring, adult fish swim up from the Atlantic to Billington Sea to spawn, and the juveniles hatched there head back out to the ocean through summer and fall. Since 2002, five dams on the brook have been removed. The Jenney Pond dam is the last one, and it is staying, repaired, with a new route built around it.

When David Gould, the town's director of energy and environment, laid out the work for the Plymouth Independent in October 2025, he described a schedule boxed in by the fish:

  1. No work on Town Brook until November 15, so juvenile herring can finish migrating to the ocean.
  2. The dam work waits on the same date. Crews cannot work on the dam under Spring Lane without lowering the water behind it, and that drawdown cannot start before November 15 either.
  3. A full pause from March 1 to June 15, while adult herring come back up the brook to spawn.

Under those limits, the heart of the in-stream season fell between mid-November and the end of February, the coldest and darkest stretch of the year. In the same article, Gould said that "no one wants us out here working during the summer tourist season." The original plan to keep clear of summer did not hold, and according to the Plymouth Independent's July 2026 reporting, the park became an active construction zone through the busy months.

In July, Gould said work would continue through the summer, fall and winter, and that crews were making sure the work did not block juvenile herring heading out to the ocean.

How a Hard Winter Became a Later Spring

Once the calendar works this way, a bad winter costs more than a few weeks. In the Plymouth Independent's July 1 update, Gould said the project was "a little bit" behind because of the harsh winter. He had hoped to open the paths by the coming New Year. His revised forecast was that the walkways would open to the public by spring 2027, with landscaping and planting going on into that spring.

"I know people really want to get here and be able to walk," Gould told the Independent. "The amount of work that's going in here, there's a lot to do: the dam repairs, the utility work, the pathways, the river work."

The fishway follows the same logic. The 2025 plan had the herring using the old fish ladder through the fall of 2026 and moving to the new bypass for the first time in spring 2027. That puts the walkway opening and the fishway's first run in the same season, and the March 1 pause in the original schedule sets a hard edge on how much in-stream work can happen before the fish come back.

What Is Already Built

A good share of the corridor is further along than the barriers suggest. As of the July update, the Independent reported:

  • The dam is largely repaired. Rock armor covers the upstream face, and a reinforced concrete wall now sits inside the dam on the upstream side.
  • The road beneath you is new. Spring Lane was removed and regraded. It now carries a new water main, a new gas line and the buried power line, and the stormwater catch basins are finished. About half the sewer line had been repaired.
  • Three culverts under the roadway are in place. These will carry Town Brook into the new fishway behind the mill, so herring can swim up, pass under the road and come out into Jenney Pond.
  • The downstream wall is replaced. A failing stone wall below the dam has given way to steel beams and concrete panels that support the dam and the roadway.
  • The channel at Market Street is deeper. Where the brook passes under Market Street, the water used to be shallow enough to stall the fish. The channel was narrowed to deepen it, and clusters of boulders now give herring places to rest out of the current.

The Market Street change is the one most residents can already see from the sidewalk. "So now, it's much easier for fish," Gould said.

The Walk That Comes Back in Spring

The finished design shows how much the walk itself is changing. The herring will no longer climb the ladder beside the mill. They will enter a nature-like fishway that winds up the slope and around the back of the building. Next to the mill, the channel will be lined with concrete and stone. A colored-concrete path will run alongside it, with animal prints pressed into the surface. Farther downstream, the stone lining drops away and the fishway becomes something closer to a natural stream.

The paths are being rebuilt for problems longtime walkers will remember. The October 2025 article described stretches between the Grist Mill and Brewster Gardens that were often muddy and sometimes underwater in storms and high tides. The old paths also had groundwater running across them, which froze in winter. The replacements are designed to be ADA-compliant, with drainage that keeps water off the walking surface. The new trail along the fishway will have lighting meant to echo the fixtures at Pilgrim Memorial State Park on the harbor.

The funding comes in separate pieces, each paying for part of what walkers will use:

Piece of the project Funding reported by the Plymouth Independent
Stream work and the nature-like fishway $10 million NOAA grant
Dam repair, Spring Lane rebuild and utilities $6.7 million in borrowing approved by Town Meeting
Footbridge over Jenney Pond and the walkways leading to it $2.7 million in Community Preservation funds
Trails from the dam to Brewster Gardens $1.5 million in Community Preservation funds

Together, those four lines come to the $20.9 million project total. As of the July report, NOAA had reimbursed the town $1.1 million for dredging Jenney Pond and another $6 million on top of that. NOAA's own fish passage funding page describes the Jenney Pond dam as the last remaining barrier to fish passage on Town Brook. The financing was still shifting this fall: Article 21 on the warrant for the October 17 Fall Town Meeting proposed paying $415,351 of the Jenney Pond dredging and restoration cost from FY2027 Community Preservation revenue rather than borrowing. The Advisory & Finance Committee recommended it 10-0-0.

Where Things Moved in the Meantime

Construction on this schedule moved businesses and events, not just paths.

The clearest example is Gillis Family Tavern. Jimmy and Brendan Gillis ran it in the Jenney Grist Mill complex along Town Brook. As the Plymouth Independent reported in July, the tavern closed that location at the end of May and planned to reopen on Main Street. Developer Rick Vayo, who owns the space at 22 Main St., visited the restaurant twice without introducing himself before signing a lease with the family. "I was very impressed with what they did," Vayo told the Independent.

Gillis Family Tavern is now open at that Main Street address. The Patriot Ledger reported on October 15 that the space was fully renovated and the tavern was back to pouring Guinness and serving wings, pizzas and sandwiches.

The herring celebration moved too. Plimoth Patuxet Museums held the 2026 Herring Run Festival at Brewster Gardens on April 25 because of the construction on Town Brook. Its announcement encouraged visitors to keep coming to the Grist Mill while the work went on.

The mill's own season follows a familiar pattern. Plimoth Patuxet lists its 2026 season as running seven days a week, 9 a.m. to 5 p.m., through the Sunday after Thanksgiving. This year that is November 29. The Grist Mill is included in the Heritage Pass and also has its own ticket. Under the original schedule, the mill's season ends about two weeks after the November 15 date set for work on the brook outside.

For anyone who wants to watch the fish use the new route, Plymouth River Herring runs a video counting program. As NOAA Fisheries has described it, an underwater camera near the Jenney Grist Mill records herring passing by, and anyone can count fish from the videos online. Those counts feed a run estimate that updates in real time. Next spring, the counts will come from a fishway that did not exist when the herring last came through.

As a Plymouth Town Meeting Member, I follow projects like the Town Brook corridor closely, because they shape what it feels like to live near downtown. If you live near Jenney Pond or Brewster Gardens and want to talk through how the finished walk and fishway could figure into your home's story, Jennifer Churchill would be glad to hear from you. Let's Connect.